Road improvements

6. Improve existing roads

Aim: Upgrades of Leach Highway, Stock Road and High Street will improve efficiency and reduce the impact of traffic on local residents.

Highlights

South West Metropolitan Corridor

The Local Impacts Committee, chaired by Tony McRae MLA, is working to identify a strategy for managing traffic on major roads in the South West metropolitan corridor, such as Leach Highway, and measures to protect local communities from the impacts of freight and general traffic.

The Committee has identified 20 ‘priority action locations' as being the places where the worst problems are being experienced now and are expected to be in the future. These locations and approximately 60 possible solutions were described to the public at two community forums held in December 2004. Community feedback has been received and is being assessed; at the same time, technical assessment of the solutions is under way.

The Committee's work will be completed in September 2005 and will lead to recommendations for a road development plan for the major roads, such as Leach Highway and Stock Road, together with ways of protecting local communities from traffic impacts such as noise.

Proposed major road improvements

To improve the efficiency of road freight movements and to encourage the transfer of road freight activities away from the Inner Harbour, three high priority, major road improvement projects are proposed. These are grade separation of the Leach Highway - Orrong Road intersection, grade separation of the Daddow Road railway level crossing and construction of the on-ramp from Abernethy Road to Tonkin Highway.

Leach Highway / Orrong Road

With regard to the grade separation of the Leach Highway - Orrong Road intersection, preliminary design work has been completed for a bridge to carry Leach Highway over Orrong Road. Proposals for design and construction of the bridge were invited from prequalified contractors in July 2005, with the contract for the bridge works to be awarded in December 2005. The bridge will be completed by December 2006. Main Roads WA has commenced community liaison, including discussion with the City of Belmont.

Progress report

Major roads in the South West Metro Corridor

Start

End

Status

Model transport activity – 2006 / 2011 / 2021 / 2031

Dec 2002

Mar 2004

Completed

Develop performance indicators – economic / social / environmental

Feb 2003

Jun 2004

Completed

Assess network performance gaps / problems

Mar 2003

Nov 2004

Completed

Identify solutions

Sep 2004

May 2005

In progress

Involve community in assessing options

Dec 2004

Dec 2004

In progress

Formulate Local Impacts Committee recommendations to Minister

Apr 2005

Jun 2005

Not started

Approval of strategy – Minister

Jun 2005

Jul 2005

Not started

DPI planning studies and subsequent MRS processes

May 2005

May 2009

Not started


Southern Link Road

Start

End

Status

Identification of freight task

Mar 2003

Mar 2003

Completed

Inventory of existing road and rail networks

Mar 2003

Mar 2003

Completed

Constraints and opportunities

Mar 2003

Jun 2003

Completed

Present Freight Task paper to Steering Group

Jun 2003

Jun 2003

Completed

Assessment of options;
Development of short, medium and long term strategies

Sep 2003

Mar 2004

Completed

Public consultation

Mar 2004

Jun 2005

Not started


Traffic management – “hotspots”

Start

End

Status

Develop a policy for managing operational heavy vehicle hotspots

Sep 2002

Sep 2002

Completed

Review project charter and clarify responsibilities

Sep 2002

Dec 2002

Completed

Develop a prioritised list of both planning and operational hotspots

Dec 2002

Mar 2003

Completed

Assign responsibility for hotspot management between DPI and Main Roads WA

Dec 2002

Mar 2003

Completed

Develop operational and infrastructure solutions

Dec 2002

Ongoing

Ongoing

Develop recommendations for solving each problem

Mar 2003

Ongoing

Ongoing

Ministerial approval
Allocation of funds
Implementation of solutions

Major works identified will be considered in Main Roads WA's annual budget process, while others will be dealt with through minor works programs undertaken on a regional basis


Traffic signals: coordination

Start

End

Status

Audit SCATS operation on coordinated routes

Sep 2002

Dec 2002

Completed

Prepare report on traffic signal coordination for Implementation Committee, including local impacts and possible initiatives

Mar 2003

Jun 2003

Completed

Report to the Implementation Committee

Oct 2003

Mar 2004

Completed


Traffic signals: advance detection

Start

End

Status

Research uses of Traffic Signal Advance Detection outside of WA

Dec 2002

Mar 2002

Completed

Report on findings, including feasibility, impacts and costs

Mar 2003

Jun 2003

Completed

Finalise report for the Implementation Committee

Sep 2003

Mar 2004

Completed